Does the law state what has to be achieved before 'completion' of the building works can be certified and, if so, can this be overridden by specific terms in the contract? Who would certify completion of building works carried out in accordance with a construction contract?

Angola

Angola

Completion of the building works is assessed and certified through a process known as handover of the works (recepção da obra), which may be requested by the contractor or at the owner’s initiative once the works are completed.

The handover is recorded in certificates of completion (autos de recepção) signed by both parties. First, there will be a provisional handover and once the warranty period against defects (that starts to run from the provisional handover date) has elapsed, a final handover takes place.

If relevant defects are detected, partial handover minutes are signed and the contractor is obliged to repair the defects within a short period of time, the length of which may vary depending on the extent of the defects.