Does the law state what has to be achieved before 'completion' of the building works can be certified and, if so, can this be overridden by specific terms in the contract? Who would certify completion of building works carried out in accordance with a construction contract?

Croatia

Croatia

Although the completion of works is not defined by law, construction of a building is considered to be completed if the building is ready for use. In accordance with the Act on Construction (Official Gazette Nos. 153/13 and 20/17), a building may be used only upon the issue of a Usage Permit, which is issued by the competent zoning and construction authority upon the performance of a technical inspection.