Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

Angola

Angola

It is common to impose a time frame for completion of the works and in public works contracts it is mandatory to indicate the time frame for completion.

A delay in completion of the works may lead to the contractor having to pay contractual fines (usually a percentage of the contract price for each day of delay), possibly payment of damages and, ultimately (the worst case scenario), to the contractor being replaced by another contractor or termination of the contract altogether.