Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

Romania

Romania

A construction contract always includes the date for completion of the works, even if it is determined by reference to a future event.

Any delay in handing over the works involves penalties being paid by the contractor. Usually, the amount of these penalties is pre-defined by the parties in the construction agreement and represents a reasonable pre-estimate of the employer's loss in the event of delay.