How are payments to contractors, design consultants and subcontractors normally structured?

Romania

Romania

Normally, in a construction contract, the price is pre agreed, taking into consideration an estimate of the costs. The employer makes an advance payment, as an interest-free loan to facilitate mobilization and the contractor submits a guarantee. The rest of the price will then be paid in instalments.

The total advance payment, the schedule of payments, and the applicable currencies and proportions, are stated in the construction contract.

A construction contract may only lay down the criteria for the subsequent determination of the price. In this situation, the works are measured and valued for payment by the engineer.

Furthermore, generally, a performance guarantee of 10 percent of the price is withheld. The performance guarantee is usually returned to the contractor in the following tranches:

  • 5 percent at the handover of the completed construction works if there are no defects identified
  • 5 percent at the final delivery at the end of the guarantee period if no defects have been identified