How are variations to the specification for engineering or construction works normally dealt with?

Angola

Angola

Private works contracts

The owner is allowed to change the scope of the works provided that its variations do not exceed 20 percent of the total price of the works, that the associated costs are paid to the contractor and that the date for completion of the works is extended. If the variations exceed 20 percent, they have to be agreed between the parties. If the changes result in a decrease of cost or work, the contractor is entitled to the agreed price with deduction of the amount saved on expenses.

Variations requested by the contractor require the owner’s consent or acceptance and the owner will not be liable for any additional costs arising from variations if they are attributable to the contractor.

If the variations are necessary and are caused by a third party or due to technical requirements, parties must agree on the price and time for completion of works, otherwise the court will decide. The contractor may terminate the construction contract if the cost of the variations exceeds 20 percent of the total works price.

Public works contracts

The additional works ordered by the owner must be the result of unpredictable circumstances and

  • Non-technical or capable of being costed separately under the contract, or
  • Necessary to the completion of the works

The contractor is required to execute additional works unless he exercises the right to terminate the contract. The owner can also determine the reduction of the works scope. When, as result of variations, there is a decrease of more than 20 percent of the initial price, the contractor may terminate the contract.

Variations requested by the contractor require the owner’s consent. If those variations result in savings, the contractor is entitled to half of its value.