What official permissions, licences or consents are required by a building or engineering contractor before it can start work?

Angola

Angola

In general, any construction activity can only be performed by the contractor if:

  • Same holds a registration title (título de registo) and, for works with value higher than AOA 3,000,000, a building contractor license (alvará de construção), issued by the Institute for Construction and Public Works Control (IRCCOP), and
  • The works to be performed are in accordance with the type and value of works that the referred title/license allows

The access to and exercise of construction activity is regulated by the Regulations on Construction Activity enacted by Presidential Decree No. 63/16, of 29 March 2016. The registration title is valid for a ten-year period and the building contractor license for a three-year period, in both cases renewable for the same period.

Furthermore, the erection of a building itself requires a building permit, which is usually applied for by the owner or developer. The procedure for the request and issuance of the building permit within the urban perimeters is governed by the Regulations on Works Licensing approved by Decree No. 80/06 of 30 October 2006. The building permits are issued by the Provincial Governments or by the Municipal Administrations.

Other administrative authorizations may be required depending on the use of the building to be erected. For example, the erection of a building for tourism or for industry usually require additional authorization from the Central Government.