During what period of time following execution of a construction contract may a party to that agreement bring a claim in the courts for breach of contract?

Angola

Angola

The general limitation period to a party to bring a claim in the courts for breach of contract is 20 years. However, claims for works defects are time-barred, a limitation period of three years following the date of completion of public construction works and a limitation period of five years following the date of completion of private construction works of buildings are the rule.