During what period of time following execution of a construction contract may a party to that agreement bring a claim in the courts for breach of contract?

France

France

Subject to the application of specific liabilities (see below), a claim for breach of a contract by one party can be brought during 5 years from the day on which this party knew or should have known the facts enabling the exercise of its right.