REALWorld Law

Construction

Other liability to end user

To what extent would an architect, another designer, the building contractor or any subcontractor have liability for any physical damage or economic loss suffered by the end-user(s) of a completed development? Can such liability be excluded in any way?

Australia

Australia

In a typical development project, there is no contractual relationship between the parties employed in connection with the design and construction of the development (the architect, engineers, other consultants, main building contractor and sub-contractors) and the end-users of the completed building.

In such a case, assuming the subsequent owner does not have the benefit of any contractual warranties from the previous owner, the subsequent owner will need to rely on the law of negligence.

Over the last 20 years, Australian law has come to recognize that building owners who suffer loss because of defective building may have a cause of action against negligent builders and others, including municipalities who by negligent exercise of their statutory responsibilities (eg inspecting foundations) allowed defective building to take place.

An action in negligence offers a subsequent owner a right of recovery against the builder of, or a relevant consultant associated with the construction of, a building in circumstances where the subsequent owner suffers a particular kind of ‘economic loss’. That is, the diminution in the value of the building in that the plaintiff has acquired property of less value than was reasonably believed, and which required the expenditure of money to restore it to the contemplated standard.

It is also possible for end-users to require the main construction parties to provide them with separate collateral warranty agreements or ‘third-party-rights’. Such collateral warranties would contain exclusion and limitation clauses which restrict the damages which end-users could recover.

It is unlikely that a contractual exclusion in favour of a builder, which has the effect of excluding or modifying any duty of care between the builder and previous owner would operate to discharge the builder from a duty of care which would otherwise exist to third parties to the contract. This is because the builder’s duty of care in such circumstances is imposed by law. However there would be difficulty in holding that a builder owes a duty of care to avoid causing economic loss to a subsequent owner if performance of the duty would have required the builder to do more or different work than the contract with the original owner required or permitted.