How are variations to the specification for engineering or construction works normally dealt with?

Croatia

Croatia

Contractual mechanisms for dealing with variations to the works vary depending on why the variation is requested:

  • Employer-led changes: Under most standard form contracts, the employer has the right to request variations to the works, for which the contractor is entitled to additional time and money. The contractor is also entitled to raise reasonable objections to material changes
  • Contractor-driven changes: Where variations are necessary due to the contractor's error, delay or default, the contractor is not usually entitled to additional time or money under the contract. He is also liable for any delays caused to the project by these variations and where the variation means that the work has not been carried out in accordance with the contract

In case of 'turnkey contracts', the agreed price includes all unforeseeable and surplus works, but the deficiency of works does not have an impact on the agreed price, unless the change of the scope of works has either been agreed by the contractual parties or has been caused by the client.