How long does it take for an initial decision to be made after receipt of an application for permission for development or the carrying on of a designated use?

Nigeria

Nigeria

The prescribed period under the relevant statutes/laws for the Control Department/Planning Permit Authority to communicate its decision to the applicant is a maximum timeline of three months from the date of submission of the application. The timelines are uncertain and may not apply depending on a variety of factors such as compliance with requirements and regulations by the applicant. In reality, the process may exceed the three months deadline.

There is no prescribed period for applications for change of designated use for property. This is dependent on the efficiency and expertise of the person processing the change of use.