Timing

How long does it take for an initial decision to be made after receipt of an application for permission for development or the carrying on of a designated use?

Nigeria

Nigeria

The prescribed period under the relevant statutes/laws for the Control Department/Planning Permit Authority to communicate its decision to the applicant is a maximum timeline of three months from the date of submission of the application. The timelines are uncertain and may not apply depending on a variety of factors such as compliance with requirements and regulations by the applicant. In reality, the process may exceed the three months deadline.

For applications involving a change of designated use, there is no specific statutory timeline. The duration for processing such applications depends on the nature of the development, submission of all required documentation, and the capacity and expertise of the officials handling the application. Applicants are therefore advised to engage with the relevant planning authority early to clarify requirements and monitor the progress of their application.