Planning / zoning

Validity period

For how long is a permission for development or the carrying on of a designated use valid?

Nigeria

Nigeria

A Planning or development permit will become invalid where development has not been commenced within two years of the grant of such permit. Where the development with planning permit is not commenced within the two-year period, the permit will be subject to revalidation by the Planning Permit Authority on the payment of prescribed fees (Section 35 (2) of the Nigerian Urban and Regional Planning Act 1992 and Section 37 of the Lagos State Urban and Regional Planning and Development (Amendment) Law 2019.

Generally, development permits have no deadline for execution of the development it relates to once construction has commenced. We however note that building construction that has been abandoned for a long time may require that the permits for its development be recertified by the appropriate government agency such as is the case in Lagos State.