Contracts for the delivery of work, including the delivery of building works, are, together with the rules of general contract law (as governed by articles 1101 – 1369 of the old Belgian Civil Code for contracts entered into before 1 January 2023 and by book 5 of the new Belgian Civil Code for contracts entered into after 1 January 2023) primarily governed by Articles 1787 and the subsequent articles of the Belgian Civil Code. For example, the latter article governs the liability of the contractor or developer and the architect, and also deals with the event of a unilateral termination of a contract.
The mandatory Law of 9 July 1971, relating to house construction and the sale of houses to be or being built (and on execution of that piece of legislation, the Royal decree of 21 October 1971), plays a dominant role in regulating contracts relating to residential construction activities. This legislation implements a number of measures to assist purchasers. In relation to consumers, some of the mandatory provisions of Book VI – Market Practices and Consumer Protection of the Belgian Code on Economic Law must also be taken into account.
Government contracts are mainly governed by the Law of 17 June 2016 on public procurements, but also by a (distinct) law of 17 June 2016 (on government concessions), the Law of 17 June 2013 (on the procedure) and the Law of 13 August 2011 (defence contracts), as well as a number of royal decrees. Considering the law on government contracts is for a large part an implementation of European Directives, the main principles of European Law (eg non-discrimination; free movement of persons, goods, services and capital) apply as well, as do the directives themselves in case they differ from the Belgian implementation.
The above laws and regulations are supported by additional sources of law, such as customs of the building industry, as well as relevant case law.
Belgian legislation does not separately deal with contracts for the design of work and therefore generally, the rules of general contract law are applicable to design work. Nonetheless, the Belgian Civil Code contains a number of articles which regulate the relationship between the architect and his principal.
Since the profession of an architect is, according to Belgian law, a regulated profession, an architect will principally also need to comply with a number of deontological or ethical rules, characteristic to the profession of an architect. An architect must be a member of the Belgian association of architects. Architects are not allowed to have any contractual relationship with contractors and must remain independent in their relationships they have with the owner / developer and with the contractors.
However, if a contracting authority aims to appoint an architect for a public contract of (design) services, it should comply with the rules set out in the aforementioned Law of 17 June 2016 on Public Procurement, together with its respective implementing royal decrees.
Last modified 13 Jun 2024
Construction works require a planning permit, which integrates the formerly separate building permit, environmental permit and socio-economic permit as of 1 January 2018. A planning permit is required for:
The legislation governing the planning permit might contravene European law, and particularly the EU Directive 2006/123/EC (the Services Directive), to the extent that it gives the awarding administration the power to withhold a permission for the aforementioned commercial developments, unless the conditions of necessity, non-discrimination and proportionality have been met) (ECJ 30 January 2018, nrs. C-360/15 en C-31/16).
Until recently, all builders working in Belgium had to comply with a number of professional requirements, mainly certifying professional competence. This requirement has been lifted for builders working in Flanders, but still apply for both Brussels and Wallonia.
Non-compliance can lead to the nullification of the building contract, so these requirements are of the utmost importance in practice.
For some construction projects, the employer must register the builders present on-site on a daily basis to Social Security, via the online registration process Checkinatwork.
When engaging foreign builders on a Belgian project, there is moreover the general obligation to file a preliminary LIMOSA-declaration to Social Security. This general obligation also applies when engaging foreign builders on a self-employed basis, as the construction sector was identified as an “at-risk sector” to which these declarations continue to apply.
Further, the employer has the obligation to verify that all foreign builders are in possession of a valid residence / work permit for Belgium during the entire duration of their assignment in Belgium.
Last modified 13 Jun 2024
The main body of Belgian health and safety law is comprised in the Law of 4 August 1996 regarding the well-being of employees in the execution of the works and its executive decrees, primarily the Code of Well-Being at Work. The Code of Well-Being at Work is a consolidation of numerous royal decrees adopted in execution of the Law of 4 August 1996, including the Royal Decree of 25 January 2001 relating to the temporary or mobile construction sites.
In addition to a number of general obligations imposed on all employers in Belgium (eg drafting of a global prevention plan and an annual action plan), additional obligations may apply to temporary or mobile construction sites, including the following:
Finally, the aforementioned legislation on public procurement (and in particular, the Royal Decree of 14 January 2013 on the general execution rules of public contracts) also contain specific provisions and obligations towards the contractor with regard to health and safety on the construction site during the execution of a public contract.
Last modified 13 Jun 2024
In the Flemish, Walloon and Brussels Capital Regions, the European directive regarding ‘Environmental Impact Assessment Directive’ (Directive 85/337/EC, consolidated as Directive 2011/92/EU) and ‘Strategic Environmental Assessment’ (Directive 2001/12/EC) are applicable to regional law. This means that for certain kinds of individual infrastructure projects, an Environmental Impact Assessment (EIA) is required and is integrated into the building and/or environmental permit procedure. For zoning plans (plans that define the public planning prescriptions that apply in a certain area), an EIA is also required, except in certain well-defined circumstances.
In the Flanders Region, the EIA legislation is contained in the Decree of 5 April 1995 containing the general principles of environmental policy (Title IV), together with its executive decrees.
In the Walloon Region, the EIA for projects and plans is integrated by the Environmental Codex of 27 May 2004 and its executive decrees.
In the Brussels Capital Region, the EIA for projects is included in the Environmental Permit Decree of 5 June 1997, and the EIA for plans and programmes is included in the Ordinance of 18 March 2004 regarding EIA for certain plans and programmes.
It is important to note that this legislation has been modified, since the European Court of Justice ruled in a judgement of 24 March 2011 (C-435/09, European Commission/ Belgium), that the EIA legislation in the Regions was not in compliance with EU law. By the Decree of 23 March 2012 the Flemish Region adapted its EIA regulation to comply with the judgement. From then on, smaller-scale projects that previously were excluded from the EIA requirement, will be screened for the need for a full EIA. This means that currently, there are EIA-mandatory projects, EIA-exempt projects and projects requiring screening in the Flemish Region.
Last modified 13 Jun 2024
Infrastructure and utilities are mostly governed by the public planning law of the Flemish, Walloon and Brussels Capital Regions, and are therefore regulated in:
In all three regions, in the case of an application for an allotment permit (which includes the construction of new roads), the Municipal Legislative Body has to decide on the infrastructure and utilities requirements, before the Municipal Council can grant an allotment permit.
Most local building regulations have been created to govern connections to sewage systems. When deciding on individual building permit applications, the municipal council usually refers to this building regulation, or imposes related conditions in the building permit.
In the case of the construction of roads, utilities and infrastructure, a separate permit procedure exists in relation to what is in the ‘public interest’. Related permit applications have to be made at Ministerial level, particularly if the application relates directly or indirectly to private project development.
Last modified 13 Jun 2024
Although there are exceptions, in general, construction contracts can be concluded orally as well as in writing (the latter being preferred for the sake of legal certainty).
No mandatory terms and conditions are imposed or implied by law, with the exception of (i) public contracts (see below) and (ii) contracts with respect to certain residential building activities, which impose mandatory requirements to include certain information in the contract to avoid the contract being deemed null and void. Such information includes:
It should also be noted that the 10-year liability rule with respect to buildings and major works cannot be contractually excluded by the architects or contractors. It is a rule of public interest as it affects public security. Briefly, this rule applies to claims based on ‘serious latent defects’ as well as defects that concern the (partial) stability of the building. In respect of such potential claims, the Belgian Civil Code provides that contractual claims against a contractor and/or an architect need to be instigated within a period of 10 years from the date of final acceptance of the related works. As this rule is governed by the Belgian Civil Code (article 1792 of the Belgian Civil Code), and is therefore of public interest in nature, it is not possible to contractually exclude the rule.
With regard to the execution of public (works) contracts, reference can be made to the aforementioned Royal Decree of 14 January 2013 on the general execution rules of public contracts. Article 9 of the aforementioned Royal Decree of 14 January 2013 enlists those provisions of the Royal Decree from which the parties cannot deviate in the contract. These mandatory provisions relate in particular to the verification and payment periods. Deviations from other than the aforementioned mandatory provisions are only permitted in duly justified cases, i.e. insofar as the special requirements of the contract so require.
According to the deontological or ethical rules applicable to architects, any contract between an architect and his client must be made in writing. Other than a number of other specified deontological rules applicable to architects (Reglement van de Beroepsplichten van de Architect), there are no other mandatory rules with respect to the content of architect contracts or contracts for the design of building works, although the 10-year liability rule (see above) cannot be set aside or excluded.
Last modified 13 Jun 2024
Various industry bodies, private and public organizations and/or associations supporting the Belgian construction and engineering sector provide standard form contracts to their members, although the use of such forms is not mandatory. International forms of contract, such as some of the FIDIC contracts, are increasingly, although not currently commonly, used in Belgium.
The selection of the form of an engineering and/or construction contract is generally dependent upon a number of factors, which include but are not limited to:
Last modified 13 Jun 2024
A construction contract is generally concluded between a contractor and the client (or principal). An engineering contract is generally concluded between an engineer and the client (or principal), or the main contractor or architect.
The relationship between the principal and the engineer or contractor is in essence contractual in nature, implying that the parties are free to contractually determine each other’s rights and obligations, subject to applicable mandatory laws.
In principle, the client or principal must enable or authorize his co-contractor (being the engineer or contractor) to carry out the work. Furthermore, the principal must accept or approve the work and will be required to pay the agreed price.
The engineer or the contractor must carry out the work in accordance with:
Unless explicitly prohibited by the contract, the engineer or the contractor can work with sub-contractors. In such a situation, the engineer or contractor will bear full responsibility towards the principal for the execution of the work.
An architect will be responsible to the principal and will come under the control of the contractor during the execution of the works. The architect will also have the assistance of the principal at the point of acceptance or approval of the work.
Under Belgian law, the builder and the architect need to be completely independent of one another. Contracts that do not guarantee such independence (e.g. with the builder appointing the architect), are voided.
Last modified 13 Jun 2024
Generally, the risks to be borne in construction or engineering contracts by the contractor or engineer respectively to the principal are subject to negotiation during the pre-contractual phase.
The allocation of risk determined by the construction or engineering contract will generally reflect the strength of the respective parties. Such allocation of risk will also depend upon the possibility and/or obligations by the parties to insure certain risks. Most construction or engineering contracts will expressly foresee a detailed risk allocation with respect to, but not limited to, price variation, timing, security and material.
Force majeure and hardship form part of Belgian general contract law. Parties can however contractually extend, limit or exclude the application of force majeure or hardship. Force majeure relieves a party from performing its obligations when unforeseen circumstances, subsequent to the conclusion of the agreement, which are not attributable to the party relying on it, make it materially impossible to fulfil the agreement. The hardship theory allows the revision of an agreement in the event of the occurrence of new circumstances, subsequent to the conclusion of the agreement, which are not attributable to the party relying on it, and if these circumstances have had a disrupting effect on the economy of the agreement, without making the execution of the agreement impossible.
In addition, the above cited public procurement legislation contains certain specific provisions on so-called unforeseeable circumstances in the execution of a public contract on part of the contractor, on the one hand, and on part of the contracting authority, on the other hand (see in particular articles 38/2, 38/9 and 38/10 of the Royal Decree of 14 January 2013 on the general execution rules of public contracts).
Last modified 13 Jun 2024
It is common in Belgium for significant infrastructure and/or building projects to be established through public-private partnerships (PPPs). Examples include the development of brownfield sites and the building of bridges and new roads, schools and sport infrastructure. The recent decade has seen an increase in PPPs, with the administration often seeking to act as a private party, before resorting to administrative acts (eg buying a plot of land before expropriating it).
In the Flanders Region, this form of co-operation is explicitly encouraged and the Decree dd. 18 July 2003 governs PPPs in Flanders. The decree contains the framework within which these partnerships are to be constructed.
In the Walloon and Brussels Capital Regions, there is no special legislation regarding PPPs, but such partnerships or forms of co-operation are however used in these regions. In the Walloon Region, the ‘Cellule d’Informations Financières’ (CIF) advises, supports, designs and implements procedures and monitoring tools on PPP projects.
PPPs are often governed by private (contract) law. If it qualifies as a public contract, the regulation regarding government contracts (see supra) is applicable.
Last modified 13 Jun 2024
Fixed price construction contracts are common. Such contracts determine that a contractor shall carry out construction works as detailed in one or more plans and/or documents, against a fixed price agreed prior to the execution of the works.
A distinction must be made between ‘firm fixed’ contracts (which contain a firm price as a whole that is not to be changed) and ‘variable fixed’ contracts, where the latter foresees a price list (with prior fixed prices for material, working hours) by which means the price of any additional work ordered by the principal will be determined.
The Law of 9 July 1971 which governs house construction and the sale of houses to be or being built, if applicable, imposes a prior fixed price regime on the execution of residential construction works.
Last modified 13 Jun 2024
Two typical categories of insurance can be distinguished:
These forms of insurance are typically obtained for construction sites.
Construction professionals are obliged to take out professional liability insurance, which covers their professional and decennial liability. Civil liability insurance must also be taken out by the safety coordinator.
There are other types of insurances which are not mandatory under Belgian law, eg construction all-risks insurance.
Last modified 13 Jun 2024
The use of parent or third-party guarantees (whether bank or otherwise) as a security for the obligations of a contractor is proportionate to the scope of the development project. A guarantee amounting to 10% of the construction price or a right for the principal to withhold 5% to 10% on the invoices to be paid to the contractor is not unusual for high-end projects. This is the so-called retention guarantee under Belgian law. Parties can agree on a 5% or 10% retention on each invoice by the owner / client / principal. Such high-end contracts typically refer to a system of double acceptance, which determines that 50% of such a guarantee will be released on the issue of the procès-verbal of a provisional acceptance, with the remaining 50% on the issue of the procès-verbal of final acceptance.
The procès-verbal is the document prepared following a visit to the construction site by the parties, prior to the provisional or final acceptance by the client of the works. The document contains details of issues relating to the works that need to be resolved prior to the handing over of the works to the client. The provisional or final acceptance by the client is subject to the signing of the procès-verbal. It is then dated and signed by the parties.
With regard to house or residential construction works, mandatory provisions relating to the provision of a guarantee are governed by the Law of 9 July 1971 which regulates house construction and the sale of houses to be or being built. This law provides for what is known as a 100% guarantee, which applies to contractors who do not comply with the requirements of the law of 20 March 1991, which governs the activities of contractors and real estate developers.
In addition, the aforementioned public procurement legislation (see in particular article 27 of the Royal Decree of 14 January 2013 on the general execution rules of public contracts) imposes the duty on a contractor to provide a guarantee for the performance cq in the execution of the contract.
Last modified 13 Jun 2024
Most contracts determine a payment schedule whereby payment instalments are due in proportion to the progress of the works. Some contracts foresee the circumstance where the contractor is required to submit pro forma statements by way of a payment procedure or structure, which is to be approved by the architect or principal within a set period, after which the contractor can accordingly submit his invoice. In this case the works can be put on hold if payment is withheld.
The Law of 9 July 1971 which governs house construction and the sale of houses to be or being built, contains a number of specific mandatory provisions which deal with payments and which are to the benefit of purchasers.
When specific conditions laid down in articles 35/6/1-5 of the act of 12 April 1965 regarding the protection of remuneration are met, the principal could be held jointly liable for serious breaches of the legal obligations to pay salary to employees committed by its direct contractor, and in some cases even by the subcontractor of its direct contractor. This joint liability could be avoided by making specific, legally defined written arrangements between the principal and its direct contractor, eg by adding a specific clause to this effect in the service agreement with the direct contractor.
Last modified 13 Jun 2024
It is common to impose in a contract a time frame for completion of the works. Where a date for completion of the works is agreed between the parties but completion does not occur on that agreed date, this will automatically imply a contractual default by the contractor. If a delay is not contractually agreed upon, a judge will determine a reasonable delay in case of dispute.
In general, a penalty mechanism in case of delay is contractually foreseen and therefore delay is dealt with in the relevant contractual document. Contracts generally foresee penalty payments for delays in the execution of the works, or for intermediary delays to agreed milestones. The contract generally specifies a lump sum damages amount per day of delay. If a “liquidated damages” clause is manifestly unreasonable, a judge may reduce the amount of the penalty, taking into account all circumstances, including actual and potential damage suffered and the legitimate interest of the claimant. The clause may not be mitigated below a minimum level that is to be considered reasonable.
The delay penalty is generally without prejudice to the principal’s right to claim any other damages on the basis of other contractual clauses.
Last modified 13 Jun 2024
A modification or alteration of the specification of an engineering or construction contract can only occur by contractual agreement between the parties. A change in the scope of the specification (for example where the extent of the works is increased or decreased) will commonly be contractually determined in engineering and construction contracts relating to major projects.
Where there is no contractual arrangement concerning a variation, and where the specification of an engineering or construction contract is unilaterally and to a major extent varied by the principal, Article 1794 of the Belgian Civil Code may apply. This article places an obligation on the principal in the event of a unilateral termination of a contract for the delivery of work, in order to compensate the contractor (ie the engineer or the contractor) for his expenses, his work and all that he could have earned if the contract had not been terminated.
In the context of a public contract, modifications are only permitted in so far as these are not material. A modification is material if:
(see in this regard articles 38/2 et seq. of the Royal Decree of 14 January 2013 on the general execution rules of public contracts).
Last modified 13 Jun 2024
Belgian law does not provide for what has to be achieved before completion of the building works can be certified. The delivery of the works will be the execution and delivery by the contractor of the contractually defined works. The contractor will meet his contractual delivery obligation by offering the executed works to the principal for certification. The acceptance by the principal is traditionally considered as an acknowledgement that the works have been completed satisfactorily.
Contracts, practice or the law provides for a mechanism known as double acceptance, which encapsulates the provisional acceptance and then final acceptance of the works by the principal. Here, the principal will usually discharge the contractor from all liabilities, except for the liabilities covered by the 10-year liability rule with respect to buildings and major works. This rule provides that after 10 years, architects and contractors are discharged from their responsibility regarding the major works they have executed or have controlled – they are therefore no longer susceptible to claims after a 10-year period.
Last modified 13 Jun 2024
As a general rule, a claim for breach of contract may be brought before the courts by any of the parties within 10 years after the breach or knowledge of the breach by the party in default.
However, according to Belgian jurisprudence, any claim relating to a light latent defect (for example the swelling of window frames), should in principle be brought before the courts within as short a period of time as possible following discovery of the defect, although the limitation period with respect to light latent defects can be contractually determined by the parties. The acceptance of the works traditionally discharges the contractor from any liabilities with respect to visible light defects known to the principal at the point that the principal provisionally accepts the works. It is however not unusual to contractually determine that the provisional or final acceptance will also discharge the contractor from any liability with respect to light latent defects.
Notwithstanding the above, a contractual discharge or contractually determined limitation period is not valid for any claim with respect to serious latent defects, which compromises the stability of the building or a major part of the building. According to Belgian public order law, any such claim can be brought before the court up to 10 years following the date of final acceptance of the works (this is known as the ‘10-year liability with respect to buildings and major works’ rule).
Last modified 13 Jun 2024
When the contractor and end user have a contractual relationship, in principle, only the rules relating to contractual liability will apply.
A contract party that does not fulfil its contractual obligations commits a contractual default as that party has not produced the promised result (in case of result engagement or the obligations to achieve a certain result) or has not carried out its obligations in the manner that would normally be expected from a normal person or entity (in case of an effort engagement being the obligation to act as any other contractor or architect or other professional would act in the same circumstances). The compensation here is limited to the damage that was foreseen or that could have been foreseen at the point of conclusion of the contract (this would reasonably include physical damage as well as economic loss), although this rarely poses a problem in practice. There is therefore a direct causal connection with the contractual default and the resulting damage.
Limitation of a contractual liability is in principle possible, except in cases where:
Last modified 13 Jun 2024
Due to lack of a direct contractual relationship between the end user and the architect, designer, contractor and/or sub-contractor, no direct claims can be made by the end user against these parties, except where the conditions for extra-contractual liability would be fulfilled (in accordance with the rules of tort). Parties are extra-contractually liable for any damage suffered by an end user, to the extent the damage is of an extra-contractual character and has been caused by their respective default or negligence, other than the wrongful undertaking of their contractual obligations. In practice, this means that one can only formulate a direct claim against the sub-contractor of one’s contract party, when the sub-contractor commits a crime while executing his obligations under the sub-contract.
As for a contractual relationship, limitation of liability is, in principle, also possible in an extra-contractual context, although in practice problems will usually arise with respect to the (silent) acceptance of a limitation of liability clause for extra-contractual damage between non-contracting parties. In such circumstances, the acceptance of a limitation of a liability clause for extra-contractual damage between non-contracting parties will take place ‘silently’ since no contract actually exists between the parties. The acceptance must be extracted out of the situation and/or the behaviour of the parties. This leads in practice to interpretation and other problems. The proof of the acceptance will not be easy to ascertain.
The only affect of limitation of liability clauses between parties and the architect, designer, contractor or sub-contractor and the principal will be that they are not enforceable against any third party or end users. Furthermore, limitation of liability clauses in favour of a contractor or an architect are not regarded favourably and in particular are opposed where they relate to the quality of buildings.
Last modified 13 Jun 2024
Due to a lack of a contractual relationship between third parties (such as purchasers, tenants and lending banks) and the contractor, the rules of extra-contractual liability generally apply. Belgian extra-contractual liability legislation will be amended quite drastically because of the introduction of a new book 6 on extra-contractual liability in the Belgian Civil Code, which was adopted by Parliament on 1 February 2024 and will enter into force six months after its publication in the Belgian official gazette.
The rules on extra-contractual liability imply that no direct claims can be made by these parties against contracting parties, except where the conditions for extra-contractual liability would be fulfilled (in accordance with the rules of tort). Parties are extra-contractually liable for any damage suffered by a third party, to the extent that (i) there is damage and (ii) it has been caused by their respective (iii) default or negligence.
In addition, related legislation provides for certain additional protection measures. For example, the 10-year liability of contractors and architects with respect to buildings and major works is considered to be a legal protection linked to the ownership rights of the building. This concerns any claim with respect to serious latent defects, which compromise the stability of the building or a major part of the building. According to Belgian public order law, any such claim can be brought before the court up to 10 years following the date of final acceptance of the works. Therefore, a claim under the 10-year liability of contractors and architects rule can be made by any of the right holders of the principal, including purchasers. The same is true for any claim for the guarantee of the principal against the contractor (eg indemnification for (hidden) deficiencies in the works), as that is considered a qualitative right accruing to any owner of the building, or a respective part of the building.
Last modified 13 Jun 2024
Construction dispute resolution in the courts is governed by Belgian general procedural law. Where a dispute arises between companies (that is to say entities that, on a permanent basis, have an economic object or purpose), the Belgian enterprise courts will have jurisdiction in such a dispute. The Belgian enterprise courts are well positioned to deal with construction disputes between professional parties, partly due to the fact that each enterprise court is headed by a president and two lay judges experienced in commercial affairs. Decisions of the enterprise courts can be appealed before the court of appeal of the district in which the enterprise court is located and this should take place, if an appeal claim is lodged, in principle, within one month after notification of the judgement of the enterprise court, provided the sum involved exceeds EUR2,500.
Last modified 13 Jun 2024
Construction disputes are generally brought before the courts. Although qualities such as speed, confidentiality, expertise and flexibility are often highlighted as advantages of arbitration in construction disputes, in practice, such advantages are often not seen as the primary benefits of arbitration due to the cost of the arbitration procedure in Belgium. Furthermore, Belgian construction contracts commonly contain a jurisdiction clause determining the competent (Belgian) court. Arbitration clauses are used less in construction contracts where the contracting parties are residing in different countries.
Last modified 13 Jun 2024
Alternative Dispute Resolution is not mandatory by law and is therefore not commonly used in construction disputes, except for matters where the determination by an expert is sought, whether appointed by the parties in agreement or in accordance with a contractual clause or appointed by the court in the context of dispute resolution.
Last modified 13 Jun 2024
In this country, what are the main rules relating to health and safety on construction sites? Do these rules in any way relate to the use of the development after construction is completed?
The main body of Belgian health and safety law is comprised in the Law of 4 August 1996 regarding the well-being of employees in the execution of the works and its executive decrees, primarily the Code of Well-Being at Work. The Code of Well-Being at Work is a consolidation of numerous royal decrees adopted in execution of the Law of 4 August 1996, including the Royal Decree of 25 January 2001 relating to the temporary or mobile construction sites.
In addition to a number of general obligations imposed on all employers in Belgium (eg drafting of a global prevention plan and an annual action plan), additional obligations may apply to temporary or mobile construction sites, including the following:
Finally, the aforementioned legislation on public procurement (and in particular, the Royal Decree of 14 January 2013 on the general execution rules of public contracts) also contain specific provisions and obligations towards the contractor with regard to health and safety on the construction site during the execution of a public contract.
Last modified 13 Jun 2024