Are any terms and conditions imposed or implied by law or mandatory in contracts for the design or carrying out of building works?

Spain

Spain

Apart from the obligation on the contractor to fulfil the technical requirements set out in the Spanish Building Act, the Spanish Technical Construction Code, the Energy Efficiency Act and other technical regulations, there are only few legal provisions implied specifically into construction contracts.

One of these provisions implied by the Civil Code is the right for the developer to terminate the contract early without cause, being obliged only to pay costs to the contractor.

An additional specific provision implied into construction contracts is that subcontractors are entitled to claim against the developer, even if no contractual relationship exists between them, for any debt owed by the contractor to the subcontractor and up to the amount owed by the developer to the contractor.