What official permissions, licences or consents are required by a building or engineering contractor before it can start work?

Poland

Poland

In accordance with Polish Building Law the construction work may only be commenced upon obtaining a decision containing the building permit. A certain number of less important construction works (for instance: construction and repair of telecommunication network, electric power network, water supply, sewage and heating networks carried along existing routes or rebuilding and repair of roads, railway tracks and railway equipment) shall not require the building permit, however the competent authorities must be usually notified of them.

It should be noted, that on 18 September 2020 the catalogue of construction works not requiring the building permit has significantly changed (as well as the catalogue of construction works, which have to be notified to competent authorities).

In some cases prior to obtaining a building permit an environmental decision should be obtained. These cases are specified in the Ordinance of the Council of Ministers dated 10 September 2019 on investments that may significantly affect the environment eg power plants, refineries, major roads, airports etc.