The main source of law is the Hungarian Civil Code (Act V of 2013) which contains the general provisions regulating contracts for the design and carrying out of building works (and contracts in general). As a main rule, these provisions are permissive, so the parties (such as the employer, contractor etc) are free to deviate from the rules contained in the Civil Code.
There are several other statutes directly governing and regulating construction in detail. The most important of these include the Construction Act (Act LXXVIII of 1997), also known as the Formation and Protection of the Built Environment Act, Government Decrees Nos. 191/2009, 194/2009, 312/2012, 266/2013 and 143/2018.
Last modified 18 Jun 2024
There are several official permissions, licences and consents to be obtained to carry out construction work, for example:
It should be noted that for special building projects additional permits may be required (eg. permits for power plants and industrial facilities).
In the case of certain retail buildings or units with a gross floor area of over 400 square meters special licensing procedures apply.
1EIA obliged activities are listed in Annex 1 of Gov. Decree 314/2005 on environmental impact assessment and unified environment use permitting procedure
2Gov. Decree 312/2012, 24-27.§
3Gov. Decree 312/2012, 21.§
Last modified 18 Jun 2024
There are several statutory regulations relating to health and safety in the workplace and on construction sites, including provisions relating to protective clothing and equipment, maintenance of a safe working environment, mandatory training and fire protection rules etc. Certain construction activities require the presence of professionals qualified in fire protection.
The parties usually agree in the construction contract that the (main) contractor will be the person liable to ensure that the health and safety regulations are complied with on the construction site. Furthermore, one of the main roles of the technical manager (who coordinates and manages the construction works) employed by the main contractor is to ensure that the works are in full compliance with the applicable laws and regulations, including health and safety regulations.1 Necessary steps are required to be taken already in the design stage preceding the construction itself (eg the designer shall appoint in advance in the process of preparing the construction master plan a coordinator for upholding occupational safety and health requirements and shall make recommendations for the completion of the working drawings from the point of view of health and safety at works). Contractors are required to use a coordinator during construction works also. The construction superintendent shall implement the coordinator’s reasoned recommendations. The contractor may begin setting up the construction site only if a safety and healthcare plan is enclosed with the construction master plan.
Following completion and takeover, liability shifts to the employer (or owner) and in practice transforms into a liability to maintain and repair the building and to keep it in a proper condition which does not endanger health and safety.2
1Gov. Decree 191/2009, 13-14.§, 4/2002 Decree of the Minister of Social and Family Affairs and the Minister of Health on minimum requirements for the protection of workers atconstruction sites and during construction processes
2Gov. Decree 191/2009, 34.§ (5), (6), Construction Act 54.§ (2)
Last modified 18 Jun 2024
The main legislation in this regard is the Environmental Protection Act (Act LIII of 1995). There are several other statutory regulations in relation to air and water protection and the disposal of waste, including construction waste. Beyond the prescriptions of the Environmental Protection Act, Decree 314/2005 on environmental impact assessment and on unified environment use authorization processes defines certain activities where mandatory preliminary environmental impact assessment shall be conducted.1
In Hungary, the ‘polluter pays’ principle applies. The owners and, if different from the owners, possessors (users) of land have joint and several liability for environmental damage or the endangering of the environment on that land. The owner may only be relieved of environmental liability if it is able to prove that it did not itself cause the damage and names the person actually liable for the pollution.2
In certain cases, where the construction project is likely to have a significant impact on the environment, an environmental impact assessment must precede the construction works.3
1Annex 1 of Gov. Decree 314/2005
2Act LIII of 1995, 102.§ (1)-(2)
3Act LIII of 1995, 68-69.§§
Last modified 18 Jun 2024
It is common for developers to sign a community development agreement with the local municipality,1 in which the developer undertakes to finance the rezoning costs of the development area, to carry out certain public works, such as landscaping or the construction of roads, public parking spaces or pavements. The works and structures so constructed would thereafter be handed over to the local municipality free of charge.
In the case of substantial greenfield developments local municipalities may participate in, and partially finance, the costs of creating the necessary utility connections.
1 Construction Act 30/A§ (1)
Last modified 18 Jun 2024
In general, the parties to a contract for the design or carrying out of building works are free to contract as they wish.1 There are, however, certain provisions that are mandatory. Such mandatory requirements include (among others):
1Civil Code 6:59.§ (2)
2Construction Act 32/A§
3Gov. Decree 191/2009. 3.§ (1); Construction Act 39/A. § (6)
4Civil Code 6:152.§
5Government Decree 181/2003 (XI.5.)
6Construction Act 39/B.§
Last modified 18 Jun 2024
No Hungarian standard form contracts exist. FIDIC and FIDIC-based construction contracts are quite widely used, especially for construction works awarded through a tender and/or public procurement.
The form of construction contract to be used is based on the parties’ agreement. However, in certain cases, such as public procurement-based construction projects, the use of a standard form contract may be required by the employer.
Last modified 18 Jun 2024
The typical parties are:
The party procuring the works being either the owner of the real property or a developer.
The party engaged by the employer/client to carry out the works. In practice, the contractor (also known as the main contractor) usually engages sub-contractors.
The parties engaged by the (main) contractor to carry out separate parts of the works.
A professional consultant who is sometimes appointed to act as a third-party certifier in relation to completion of the works.
Usually involved in more complex projects where his main tasks are to coordinate all parties involved and (eventually) to enter into contracts on behalf of the developer.
Employed by the contractor, his or her main roles are to coordinate and manage the construction works on site and to ensure that the works are in full compliance with the applicable laws and regulations.
In certain cases, technical inspector shall be engaged by the employer (eg when construction activities are subject to record construction log). His or her duties are – among others – to ensure that the works are in full compliance with the applicable laws and regulations, with the binding building permit and with the approved technical documentation.1
Banks or other financial institutions providing finance to any of the parties.
Involved if the works are subject to ‘project fund management’ under the Construction Act (Act LXXVIII of 1997), the project fund manager distributes the funds provided by the client to the contractor, monitors the invoicing and payment of contractors’ fees within the subcontractor chain and through various tools ensures that all subcontractors are paid for approved performance.2
1Gov. Decree 191/2009. 16. §
2Construction Act 39/B.§
Last modified 18 Jun 2024
The contractor is responsible for the construction of the works, including pre-financing the project milestones (though sometimes employers/clients agree to pay an advance amount), health and safety on the construction site and property protection etc. In design and build projects, the contractor is not only responsible for the construction, but also for the design of the works.1
The employer is responsible for – among others – ensuring full funding of the project and also to hand over the construction site to the contractor.2
The employer and the contractor shall be subject to joint and several liability for having the construction debris removed from the construction site, to restore the surrounding areas and the surface of the terrain to its original condition or as authorized, and to clean up any damage made to the environment.3
In relation to force majeure, if the contractor is unable to perform its obligations (eg completion by a specified date) under the construction contract because of unforeseeable events outside its control, this might result in the extension of the original time for completion. If performance becomes impossible for a reason that is outside the contractor’s control, the contractor shall be entitled to a proportionate amount of the remuneration for the work already performed and for his expenses.4 The employer shall be entitled to demand the contractor to deliver any works in progress, which are not yet finished.5
1Civil Code 6:252.§, Construction Act . 40.-41 §§ (1), Gov. Decree 191/2009 12.§ (2)
2Construction Act 43. § (1)
3Construction Act 43. § (2)
4Civil Code 6:248.§ (1) c.)
5Civil Code 6:248. § (2)
Last modified 18 Jun 2024
The use of public-private partnerships (PPP) used to be widespread until 2010. The government and particularly municipalities did encourage PPP projects as such projects allowed them to focus on delivering the core services they are required to provide. Since 2010 virtually no new PPP projects have been started.
Last modified 18 Jun 2024
Yes, it is possible to enter into a fixed price construction contract. In fact, fixed price construction contracts are rather common in Hungary. In such cases, the contractor is not entitled to any additional money for works included in the design and the technical specifications.
Nevertheless, if there are any variations to the works instructed by the employer, the contractor may request compensation for such extra works.1
1Civil Code 6:244-245.§
Last modified 18 Jun 2024
There are no insurances required by law. Nevertheless, pursuant to the construction contract, contractors may be obliged to take out, at their own expense, certain insurances relating to the works to be carried out. Such insurances typically include:
1Construction Act 39. § (5)
2Gov. Decree 191/2009 42.§ (9);
Last modified 18 Jun 2024
In Hungary, it is not usual to provide other security documents in addition to the construction contract, although sometimes parent company guarantees are provided by the employer if the employer is a special purpose vehicle.
To ensure that the funds earmarked for certain construction and building activities are used for the purposes specified in the construction contract, the Construction Act, requires the employment of a project fund manager for construction works exceeding currently the value of EUR5,382,000.1 The most important aspect of ‘project fund management’ is that the funds to cover the costs of the construction works must be deposited in advance into a separate account accessed exclusively by the project fund manager who is responsible for the distribution of these funds to the contractor and sub-contractors. Construction concessions and works awarded through public procurement are not subject to ‘project fund management’.2
The employer and the contractor might agree in the construction contract that a certain part of the contract price will not be paid at completion, for example 5% of the contract price is withheld until the occupancy permit relating to the works to be carried out becomes final and non-appealable, and an additional 5% is withheld until the expiry of the guarantee period. It is also common that the parties agree on the provision of a bank guarantee covering the potential warranty and guarantee claims of the employer during the guarantee period.
1 Actually applicable thresholds are published yearly on the website of the Public Procurement Authority of Hungary; https://www.europarl.europa.eu/contracts-and-grants/en/public-procurement.
2Gov. Decree 191/2009, 17.§ (2) b.)
Last modified 18 Jun 2024
Although the method of payment is subject to the parties’ agreement, the most typical scenario is that payment is made after completion of each milestone.
Fixed-price contracts are common in Hungary, although other payment and calculation methods are also in use, including prime cost and cost plus fee arrangements. The contractor may become entitled to additional payment(s) if variations to the original technical specifications are requested by the employer.1
To ensure that the funds earmarked for certain construction and building activities are used for the purposes specified in the construction contract, the Construction Act, requires the employment of a project fund manager for construction works exceeding the current value of EUR5,382,000. The most important aspect of ‘project fund management’ is that the funds to cover the costs of the construction works must be deposited into a separate account accessed exclusively by the project fund manager who is responsible for the distribution of these funds to the contractor and sub-contractors. Construction concessions and works awarded through public procurement are not subject to ‘project fund management’.
1 Civil Code 6:245.§
Last modified 18 Jun 2024
The parties are free to agree on a fixed completion deadline.1
If there is a delay in completing the works by the date specified in the construction contract, the employer may bring a claim against the contractor for general damages for late completion. In addition, construction contracts usually include liquidated damages provisions (a liquidated damages clause) in which an amount or a percentage of the contractor’s fee is set forth as applicable for each calendar day of the delay until the maximum amount, also defined in the contract, is reached. It is important to note that excessive liquidated damages may be reduced by the court.2
As to late payment by the employer, the contractor may become entitled to late payment interest.3
1Civil Code 6:35.§ (1)
2Civil Code 6:186-189.§
3Civil Code 6:48.§
Last modified 18 Jun 2024
As a general rule, the employer may instruct the contractor and request variations to the construction works. If the requested variations affect the original technical specifications, the contractor may become entitled to additional fee(s) and extra time for completion.1
1 Civil Code 6:244.§
Last modified 18 Jun 2024
The building works are taken over by the employer when completion of the works has been reported by the contractor to the employer. In certain cases, a trial operation lasting for at least 30 days is also required. As part of the takeover procedure, the employer inspects the works and any deficiencies, defects and warranty claims are recorded. Minor defects not affecting ordinary use usually do not entitle the employer to reject taking over the works.1
For the purpose of issuing the occupancy permit the representatives of the relevant authorities also conduct a site visit in order to determine whether the works have been carried out and completed in compliance with the applicable laws, regulations and the building permit and whether the works are suitable for the intended use and occupation.
The parties may also agree that the certification of completion is referred to a third-party certifier, such as an architect or engineer. This is also common in FIDIC (and FIDIC-based) construction contracts.
1 Civil Code 6:247.§
Last modified 18 Jun 2024
The general limitation period, including the period available to file claims for damages, is five years.1
Guarantee claims can be made within the deadline set forth in the construction contract. In certain cases, the (minimum) guarantee period is prescribed by law.
1 Civil Code 6:22.§ (1)
Last modified 18 Jun 2024
Provided that the developer and the end user have contractual relationship, the developer is liable for any physical damage or economic loss suffered by the end user in accordance with the general liability rules for breach of contract. Limitation (including exclusion) of developer’s liability for the construction of the works may only be possible if there is an adequate compensation (eg. a price reduction) for such limitation. In certain cases however, the developer’s liability may not be validly excluded including bodily injury damage to health, and for damages caused by wilful misconduct or a criminal act.1
1 Civil Code 6:142.§; 6:152.§
Last modified 18 Jun 2024
Due to the lack of contract between the architect/designer/(sub-)contractor and the end user, the latter may enforce its claims against the architect/designer/(sub-)contractor for damages in accordance with the general tort liability rules, pursuant to which a person causing damage to another person in violation of the law shall be liable for such damage and may only be relieved of liability if he is able to prove that he has acted in a manner that can generally be expected in the given situation. The period of limitation for such claims is, as a general rule, five years.1
1 Civil Code 6:519.§
Last modified 18 Jun 2024
Due to the lack of contract between the designer/contractor and the purchaser/tenant/bank as affected third party, the latter may enforce its claims against the designer/contractor for damages in accordance with the general tort liability rules, pursuant to which a person causing damage to another person in violation of the law shall be liable for such damage and may only be relieved of liability if he is able to prove that he has acted in a manner that can generally be expected in the given situation.1
Additionally, developers tend to assign all rights under design/construction contracts to the end users, allowing them to sue the designers/contractors for breach of contract directly.
1 Civil Code 6:519.§
Last modified 18 Jun 2024
The general ordinary courts deal with construction disputes as no specialized courts exist for this purpose. However, technical experts/consultants are often involved, including the Performance Certification Expert Board, which at the request of the parties (eg the contractor or designer) will deliver an expert opinion as to whether the contractor’s performance complied with statutory requirements and the conditions of the construction contract.1
Claims of lesser value will start in a district court, whilst more substantial claims will be heard in a regional court (in Budapest, this is the Metropolitan Court). First instance decisions of the ordinary courts can be appealed either to the regional court (Metropolitan Court) or the Regional Court of Appeal depending on which court acted as the court of first instance. The ultimate court of appeal through the supervisory proceedings is the Curia (Supreme Court of Hungary).2
1 Act XXXIV. of 2013
2 Act CXXX of 2016 on Civil Procedure
Last modified 18 Jun 2024
It is quite common in Hungary that construction disputes are referred to arbitration. The Court of Arbitration attached to the Hungarian Chamber of Commerce and Industry is a popular arbitration court. The use of arbitration is always based on the decision of the contracting parties and their choice must be included in the construction contract.
The advantage of the use of arbitration as a method of dispute resolution is that it is significantly faster than the ordinary litigation proceedings and, unlike the decision of an ordinary court, the decision of an arbitration court cannot be appealed. One drawback is that arbitration is considerably more expensive than litigation through the ordinary courts.
Last modified 18 Jun 2024
The contracting parties are free to refer their construction dispute to ADR. Expert determination is typical where resolving the issue in dispute requires special skills and expertise. Experts are usually appointed by the mutual agreement of the parties and, similarly, the related costs are borne equally. To avoid any doubts and interpretation conflicts, the provisions for expert determination (if applied) should be included in detail in the construction contract.
Mediation is a relatively new form of ADR in Hungary and has a growing popularity. As a related obligatory requirement, legal entities must first attempt an out-of-court settlement of their dispute before filing a claim with the court.
Last modified 18 Jun 2024
What insurances need to be put in place by law or under a typical construction contract?
There are no insurances required by law. Nevertheless, pursuant to the construction contract, contractors may be obliged to take out, at their own expense, certain insurances relating to the works to be carried out. Such insurances typically include:
1Construction Act 39. § (5)
2Gov. Decree 191/2009 42.§ (9);
Last modified 18 Jun 2024