REALWorld Law

Construction

Delay

Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

Australia

Australia

Construction contracts require the works to be completed by a specified date. Instead of the employer bringing a claim for general damages (compensation) for late completion of the works by the building contractor, it is standard for the contractor to be required to pay what are termed 'liquidated damages' (LDs).

Liquidated damages are damages that are fixed and the amount is agreed by the parties in advance. A typical clause requires the building contractor to pay or allow the employer to deduct liquidated damages at a rate per day or week of delay in the completion of the works. The rate is usually set out in an appendix to the construction contract.

Contractual provisions for the payment of such sums are common in building contracts and favoured because:

  • In some situations, it can be difficult and costly to ascertain the actual loss suffered by the employer
  • LDs avoid the employer having to prove its loss by claiming general damages and avoid arguments over remoteness of damages
  • The contractor is often keen to fix the level of its liability to the employer for late completion
  • LD provisions save the time and cost of litigating over the amount of such loss

It is important to note that:

  • If included in a contract, liquidated damages will be the only remedy for delay available to the employer.
  • In order to be enforceable, liquidated damages must represent a genuine pre-estimate of the loss likely to be caused to the employer by the contractor's failure to complete on time. If they are not a genuine pre-estimate, then they may amount in law to a penalty and penalties are unenforceable under Australian law.