REALWorld Law

Construction

Delay

Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

UK - England and Wales UK - England and Wales

UK - England and Wales

Construction contracts require the works to be completed by a specified date. Instead of the employer bringing a claim for general damages (compensation) for late completion of the works by the building contractor, it is standard for the contractor to be required to pay what are termed ‘liquidated and ascertained damages’ (LADs) or, more simply, ‘liquidated damages’ (LDs).

LADs are damages that are fixed and the quantum is agreed by the parties in advance. A typical clause requires the building contractor to pay or allow the employer to deduct LADs at a rate per day or week of delay in the completion of the works. The rate is usually set out in an appendix to the construction contract.

Contractual provisions for the payment of such sums are common in building contracts and favoured because:

  • in some situations, it can be difficult and costly to ascertain the actual loss suffered by the employer;
  • LADs avoid the employer having to prove his loss by claiming general damages and avoid arguments over remoteness of damages;
  • the contractor is often keen to fix the level of his liability to the employer for late completion; and
  • LADs provisions save the courts’ time.

It is important to note that, (1) if included in a contract, LADs will be the only remedy for delay available to the employer, and (2) in order to be enforceable, LADs must represent a genuine pre-estimate of the loss likely to be caused to the employer by the contractor’s failure to complete on time. If they are not a genuine pre-estimate, then they may amount in law to a penalty unless there is a commercial justification for the level of damages used – penalties are unenforceable under English law.