Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

Hungary

Hungary

The parties are free to agree on a fixed completion deadline.

If there is a delay in completing the works by the date specified in the construction contract, the employer may bring a claim against the contractor for general damages for late completion. In addition, construction contracts usually include liquidated damages provisions (a liquidated damages clause) in which an amount or a percentage of the contractor’s fee is set forth as applicable for each calendar day of the delay until the maximum amount, also defined in the contract, is reached. It is important to note that excessive liquidated damages may be reduced by the court.

As to late payment by the employer, the contractor may become entitled to late payment interest.