REALWorld Law

Construction

Delay

Is it possible for the parties to a construction contract to agree that the time/date for completion of the works is to be fixed? How would delay be dealt with?

Nigeria

Nigeria

Construction contracts generally specify the duration of the contract and the date of completion of the contract and the contractor is expected to comply with this provision failing which he will be deemed to be in default except where the delay is caused by the employer or by a force majeure event in which case the contractor is excluded from liability.

Where the delay is caused by the employer, invariably the contractor should be entitled to an extension of time for completion. In the event that the delay is caused by the contractor, the employer is entitled to claim for extra costs and inconveniences arising therefrom against the contractor.

Construction contracts usually make provision for liquidated damages which are a means of compensating the employer when the contractor does not complete his works within a stipulated time agreed. Any extra time required to complete the project will result in a deduction at a predetermined rate under the contract calculated per day, week, or month that the works are delayed beyond the agreed completion date. There is a limit to the amount that can be claimed as liquidated damages and usually not exceeding a specific percentage of the total contract price.

Another option open to an employer where the contractor fails to deliver within the fixed time agreed by the parties or where there has been undue delay in the performance of the contract by the contractor, is that the employer may opt to rescind or cancel the contract.