What official permissions, licences or consents are required by a building or engineering contractor before it can start work?

Hungary

Hungary

There are several official permissions, licences and consents to be obtained to carry out construction work, for example:

  • Environmental impact assessment (EIA): in certain cases, where the construction project is likely to have a significant impact on the environment, an EIA must precede the construction works.
  • Preliminary building permit: this is a preliminary permission to ascertain the main requirements and conditions applicable to the projected building works. The preliminary building permit is valid for one year.
  • Building permit: in most cases, this is required for construction work to start. As a rule, the construction works must start within four years from the date when the building permit became final and binding. The works must be completed in a ‘ready-for-occupancy’ condition within six Such deadlines may not be extended.  If the works are not started or completed within the applicable deadlines then the building permit becomes ineffective and a new building permit must be obtained.

It should be noted that for special building projects additional permits may be required (eg permits for power plants and industrial facilities).

In the case of certain retail buildings or units with a gross floor area of over 400 square meters special licensing procedures apply.