REALWorld Law

Construction

Licences and permits

What official permissions, licences or consents are required by a building or engineering contractor before it can start work?

Italy

Italy

A contractor may be required to obtain various permits and/or exemptions from zoning plans before it can commence the construction of a project. These are as follows.

  • A building permit is generally required.
  • If the design for a public building or a public facility conflicts with the zoning plan, an exemption from the zoning plan must be granted to obtain a building permit.
  • If the design for a private construction project conflicts with the zoning plan, a variation of the zoning plan must be granted to obtain a building permit.
  • A demolition permit may be required.
  • A felling permit may be required to remove any green areas.
  • Planning permission may be required in connection with infrastructure.
  • If the area where the building is located is affected by some public liens – as, for instance, the landscape or the hydrogeological one – the obtainment of a preliminary authorization by the competent public body is required
  • If the building is subject to the cultural lien pursuant to the Legislative Decree 42/2004, the works shall be authorized in advance even by the competent Superintendence for the Cultural Heritage.

Whether or not a specific permit is required depends mainly on the type of construction.

Construction activity is subject to a building licence, issued by or filed with the competent local administration board/committee. Four types of licence exist:

  1. a building permit;
  2. a certified notice of commencement of works (Segnalazione certificata di inizio attività SCIA);
  3. a formal notice of commencement of works (Comunicazione di inizio lavori asseverata); and
  4. 4. a notice of commencement of works (Comunicazione di inizio lavori CIL).

Building permit

The building permit is an administrative licence issued by the competent local administration committee to allow the construction in compliance with the relevant town planning provisions.

When applying for the licence, the property owner must present plans for construction, prepared by a professional expert (for example, an engineer or architect) registered with the competent professional board, specifically describing the technical specifications of the construction works.

If the local board of administration approves the project, the building permit is granted. However, if the construction works relate to particular area for which special rules are established (for example, environmental, architectural and artistic) the issuance of the construction permit is subject to the board’s prior approval.

SCIA

In relation to construction works, a simplified type of building licence called a SCIA is allowed. The property owner must merely communicate to the competent local authority the beginning of the construction works.

The contractor can begin the works on or after the date of submission of the notice.

However, within 30 days from the submission, the competent authority checks the notice and whether it complies with the relevant legal requirements and local regulations and, where there is a proven failure to comply with relevant legal requirements and conditions, prohibits further activity and orders the remediation of potentially harmful work already carried out.

CILA - CIL

In relation to some minor construction works, simplified types of building licences called CILA and CIL are available. The property owner must merely communicate to the competent local authority that construction works are to commence.

The construction works can begin on or after the date of submission of the notice.

The authority may check whether the notice complies with the relevant legal provisions and local regulations.