Construction

Licences and permits

What official permissions, licences or consents are required by a building or engineering contractor before it can start work?

Nigeria

Nigeria

The Construction Industry is well regulated by laws which prescribe certain requirements for commencement of any development. The nature of the development or construction determines the process to be followed and the licence and approval required by a building or engineering contractor to commence work.

The permits and licenses required to commence a development construction include the following:

  • Title and right of occupancy over the land upon which the development is to be constructed. This is mostly for private developments and may not be necessary for a public project on state land where the state is the sponsor;
  • Relevant certifications from the appropriate statutory bodies must be obtained by the professionals (Engineers, Architects, Surveyors, Builders, etc.) involved in the construction process;
  • Building design approvals and development permits from the appropriate state department/authority;
  • Environmental Impact Assessment Clearance and Compliance permit;
  • Relevant Fire, Health and Safety permits and licenses; and
  • Sub-soil Investigation Report is required in the case of structure in excess of two (2) floors and all developments in areas with low bearing capacity soils.

Under the extant regulations, every building development or project construction requires the inspection by relevant technical officials and certifications of compliance on quality and approved specifications.