Limitation period

During what period of time following execution of a construction contract may a party to that agreement bring a claim in the courts for breach of contract?

Nigeria

Nigeria

The Limitation of Actions Act 2004 (as amended) and the relevant States Limitation Laws prescribe the specific periods within which legal actions are to be commenced or instituted from when the injury or omission, causing the damage or loss, arose or occurred. The prescribed period for contracts under Sections 8 (1) (a) and 12 (1) (a) of the Limitation Law of Lagos State 2015 is six years for simple contracts and twelve years for contracts under seal (made by way of a Deed).

Typically, most construction contracts are made by way of deed. A claim for breach of the contract must be commenced within 12 years from the date the event giving rise to the breach occurred. In the event that the construction contract is not made by way of a deed, a simple contract, the limitation period is six years.