Construction

Developer's liability to end user

To what extent would a person who procures or carries out building works have liability for any physical damage or economic loss suffered by the end user(s) of the completed development? Can such liability be excluded in any way?

Croatia

Croatia

Any person carrying out construction works is liable to the investor as well as to any further person who acquires the building for any defect in the substantial parts of the building which appears within ten years from the completion of the construction and for any defect in other parts of the building which appears within two years from the completion of the construction. The same liability applies to the designer if the defect results from a defect in the project and to the supervisor if the defect results from a mistake in the supervision. This liability may not be excluded.