During what period of time following execution of a construction contract may a party to that agreement bring a claim in the courts for breach of contract?

Portugal

Portugal

The general limitation period is 20 years. However, claims for defects are time-barred after five years following the date of completion of the construction works. A longer period may be agreed by parties.