REALWorld Law

Planning / zoning

Timing

How long does it take for an initial decision to be made after receipt of an application for permission for development or the carrying on of a designated use?

Belgium

Belgium

In the Flemish Region, the decision will usually be made within a period of 105 days after its delivery by the applicant. This often becomes 120 days if the advice of the advisory council is needed. For applications within the scope of the 'simple procedure', a decision will be delivered within 60 days.

In the Brussels Capital Region, the municipal council makes its decision within 45, 75, 90 or 160 days, depending on whether the advice of the public planning officer is needed or not, and/or whether special rules apply for the publication of the decision.

In the Walloon Region, the municipal council generally sends its decision to the applicant within a period of 30 to 115 days (with possible increase of 30 days) depending on whether the advice of the public planning officer is needed or not, and/or whether special rules apply for the publication of the decision.